This is the same Van Buuren Municiple Drain that we have been flooding from upstream.
Van Buuren Drain Flood Relief Alliance
VDFRA is a non-profit Advocate for flood relief in Southern Ontario.
Wednesday, December 7, 2016
Severe Flood In Centennial Park, Grimsby Ontario
Footage of the huge flood in Grimsby, Ontario, August 5th, 2008. This
severe storm flooded half of Centennial Park(Nelles Park), and some
parts reached depths of 6 feet.
This is the same Van Buuren Municiple Drain that we have been flooding from upstream.
This is the same Van Buuren Municiple Drain that we have been flooding from upstream.
Labels:
climate change,
drainage,
flooding,
floods,
Grimsby,
municiple drain,
van buuren drain,
vanbuuren drain
Stoney Creek homes flooded out again
Glanbrook councillor Brenda Johnson was so angered by what she
saw walking around her ward after the record rainfall Jan 13, which
produced flooding across Mount Hope and Winona, that she questioned
the city’s new residential development strategy.
“I was so frustrated yesterday,” said Johnson, during a Jan. 14 government issues committee meeting. “With wet feet, I was touring the area and I was questioning the development. I’m not here to deter development, but I want to make sure it doesn’t contribute to it.”
She said there were 15 areas in Binbrook, and Mount Hope where new residential homes are being constructed up against established homes, are now experiencing flooding issues. Some of those homeowners suffered thorough severe flooding problems in July during a concentrated rain fall that resulted in 160 people complaining to the city.
She saw some of the same homeowners have more flooding issues. In addition, there were homeowners along McNeilly Road who had to deal with problem flooding.
“There are brand new homes that have never been flooded before,” she said. “We have got to look at this.”
While city officials trumpeted Hamilton’s record-breaking building permit results of $1.5 billion for 2012, passing the 2010 record of $1.06 billion, Stoney Creek councillors were focused on the new developments in their areas as partly responsible for the flooding issues.
Stoney Creek councillor Brad Clark said Green Acre Park flooded out the surrounding area, the first time that has happened. He said along Upper Stoney Creek 5,000 homes are being built, putting even more pressure on where the water will be going in the surrounding area and in lower Stoney Creek.
“I have seen brand new developments that shouldn’t have flooding,” said Clark.
Since September,Clark said there have been flooding problems along such roads as Fox meadow Dr., Highland Road, Highgate, Candlewood Dr., Hillcroft Dr., Highbury, Byron, Leckie Av.,Springarden Cres., and Fairhaven Dr.
“We are seeing new flooding,” he said.
Ward 10 councillor Maria Pearson said after the Sunday rainfall there was flooding in existing neighbourhoods in her area, especially areas that have recently see new homes built.
“There has been no rhyme or reason to this flooding,” she said.
Johnson asked city staff to inform her what she should tell her homeowners who have been flooded out of their homes.
“I received an email from a person who been living in his house for eight months, and this is the second time they have had flooding,” said Johnson.
Tony Sergi, senior director, growth management, said the city’s development standards should be “helpful” to prevent flooding. But if residents experience multiply flooding incidents, “we should look at it,” he acknowledged.
Clark and Johnson introduce a motion at the Jan. 15 planning committee meeting to have staff peer review the designs of three storm water ponds in the hardest hit areas.
“We want to make sure things are what they say they are,” said Johnson.
Hamilton received about 44 mms of rain Jan. 13, a new record, breaking the one set in 11.4 mm in 1979, stated Enviornment Canada. The rain fell from Saturday and Sunday, and it combined with a record high temperatures. Again, Hamilton’s 13.3 Celsius broke old record of 12.1 degrees in 1995. The heavy rains, plus the high temperatures contributed to flooding across the Mountain including at Mohawk Road and Upper Ottawa Road, where the catch basins were blocked, and in the Rosedale neighbourhood.
In July, the city received about 160 residents complaining about flooding issues after 66 mm or rain fell in a severe rain storm that hit only specific areas around the Hamilton, and Grimsby areas.
Councillors late last year re-funded the city’s protecting plumbing program which provides homeowners about $2,000 to install sewage backflow valves or sump pumps to prevent flooding issue.
Source: http://www.hamiltonnews.com/news-story/5426208-stoney-creek-homes-flooded-out-again/
“I was so frustrated yesterday,” said Johnson, during a Jan. 14 government issues committee meeting. “With wet feet, I was touring the area and I was questioning the development. I’m not here to deter development, but I want to make sure it doesn’t contribute to it.”
She said there were 15 areas in Binbrook, and Mount Hope where new residential homes are being constructed up against established homes, are now experiencing flooding issues. Some of those homeowners suffered thorough severe flooding problems in July during a concentrated rain fall that resulted in 160 people complaining to the city.
She saw some of the same homeowners have more flooding issues. In addition, there were homeowners along McNeilly Road who had to deal with problem flooding.
“There are brand new homes that have never been flooded before,” she said. “We have got to look at this.”
While city officials trumpeted Hamilton’s record-breaking building permit results of $1.5 billion for 2012, passing the 2010 record of $1.06 billion, Stoney Creek councillors were focused on the new developments in their areas as partly responsible for the flooding issues.
Stoney Creek councillor Brad Clark said Green Acre Park flooded out the surrounding area, the first time that has happened. He said along Upper Stoney Creek 5,000 homes are being built, putting even more pressure on where the water will be going in the surrounding area and in lower Stoney Creek.
“I have seen brand new developments that shouldn’t have flooding,” said Clark.
Since September,Clark said there have been flooding problems along such roads as Fox meadow Dr., Highland Road, Highgate, Candlewood Dr., Hillcroft Dr., Highbury, Byron, Leckie Av.,Springarden Cres., and Fairhaven Dr.
“We are seeing new flooding,” he said.
Ward 10 councillor Maria Pearson said after the Sunday rainfall there was flooding in existing neighbourhoods in her area, especially areas that have recently see new homes built.
“There has been no rhyme or reason to this flooding,” she said.
Johnson asked city staff to inform her what she should tell her homeowners who have been flooded out of their homes.
“I received an email from a person who been living in his house for eight months, and this is the second time they have had flooding,” said Johnson.
Tony Sergi, senior director, growth management, said the city’s development standards should be “helpful” to prevent flooding. But if residents experience multiply flooding incidents, “we should look at it,” he acknowledged.
Clark and Johnson introduce a motion at the Jan. 15 planning committee meeting to have staff peer review the designs of three storm water ponds in the hardest hit areas.
“We want to make sure things are what they say they are,” said Johnson.
Hamilton received about 44 mms of rain Jan. 13, a new record, breaking the one set in 11.4 mm in 1979, stated Enviornment Canada. The rain fell from Saturday and Sunday, and it combined with a record high temperatures. Again, Hamilton’s 13.3 Celsius broke old record of 12.1 degrees in 1995. The heavy rains, plus the high temperatures contributed to flooding across the Mountain including at Mohawk Road and Upper Ottawa Road, where the catch basins were blocked, and in the Rosedale neighbourhood.
In July, the city received about 160 residents complaining about flooding issues after 66 mm or rain fell in a severe rain storm that hit only specific areas around the Hamilton, and Grimsby areas.
Councillors late last year re-funded the city’s protecting plumbing program which provides homeowners about $2,000 to install sewage backflow valves or sump pumps to prevent flooding issue.
Source: http://www.hamiltonnews.com/news-story/5426208-stoney-creek-homes-flooded-out-again/
Labels:
bin brook,
climate change,
drainage,
environment canada,
flooding,
floods,
glanbrook,
Grimsby,
hamilton,
mount hope,
rain,
stoney creeek,
winona
STORM KO'S HYDRO, CAUSES FLOODING IN GRIMSBY
Another summer storm lashed Grimsby with hail, high winds and heavy rain on Tuesday.
The storm hit Grimsby and parts of Beamsville at about 6:05 p. m. on Aug. 5, reported Niagara Regional Police, knocking out hydro and causing flooding and downing trees throughout the area.
Police responded to several reports of trees blown over, branches falling and road flooding causing traffic hazards, as well as a dozen alarms.
Grimsby Power was kept busy restoring hydro service to areas affected.
There was a small electrical fire reported on Ridge Road, two trees were knocked over at the Grimsby Library, and there was some flooding at Beamsville Secondary School.
Niagara Regional Police had flooding of their own at the Grimsby District office, 25 Bartlett Ave. The power was out for a short time and so were the phones at the station. Heavy rains poured in through the lower garage flooding areas of the basement from three to five inches deep with muddy water.
Damage was limited to several boxes of paper supplies, and the Regional Works attended to assist with the clean up of the mud. Operations of the Grimsby office are not affected by this minor flooding.
Source: http://www.wellandtribune.ca/2008/08/07/storm-kos-hydro-causes-flooding-in-grimsby
Niagara region recovering from flooding
It was an overnight
deluge in the western end of Niagara that flooded roads and buildings
and washed out a section of the main CN rail line west of St.
Catharines. Rail service along that line has been shut down
indefinitely — affecting not only freight trains but also Amtrak
and GO train passenger service from Toronto to Niagara Falls.
The damage is bad.
Torrents of water washed out a section of the CN Rail line foundation
west of Seventh Street in St. Catharines. A freight train is on the
other side. It’s blocked. The line is shut down. CN has no timeline
on where it will be repaired.
Freight trains are
being re-routed. Amtrak train service is disrupted.
When Steve and Renee
opened their basement door this morning, everything down there was
floating in water.
Renee Coulter,
flooded basement: “We could barely see our top stairs in the
basement. It was water. Water everywhere.”
Henk Sikking heard
the storm and the torrential downpour: “I had no idea how much
water until 5:30 this morning when my wife woke up and said the
neighbour’s are flooded.”
Henk walked into his
greenhouse at Pioneer Flower Farms this morning: “In some places,
we had over two feet of water in our greenhouse.”
He took these
pictures of plants floating out the front door.
The thunderstorm was
concentrated in an area between St.Catharines and Vineland. About 110
millimetres of rain fell overnight. That’s about five inches in a
matter of hours.”
There were pumps
going all over the place. Growers we talked to say they’ve never
seen this much water in the orchards and fields.
Dave Wall is a
tender fruit grower: “The land was a little dry. And to have the
land soak up all that water and then have all the ponding and
washouts. It must have really been bad.”
Roads were
crumbling. This driveway was destroyed. Fourth Avenue in St.
Catharines looked like a small lake. This section was closed all day.
Steve Brooker had a
flooded basement: “It was one of those days where you don’t know
what mother nature’s going to bring you. Yesterday was a nice sunny
day. The next thing you know, you’re under water.”
There was no Amtrak
service through Niagara today. Amtrak was bussing passengers between
Aldershot to Buffalo and Buffalo to Toronto and they’ll continue to
do that until the rail line is repaired. We just don’t know when
that will be.
Labels:
conservation authority,
flooding,
floods,
niagara region,
NPCA
Worries over new flood plain maps
A former West
Lincoln alderman is calling for an outside review of a proposal by
the Niagara Peninsula Conservation Authority to adjust flood plain
maps for the Welland River.
Norm Johnson joins
several residents affected by the changes in calling for a public
process and secondary review of the new flood plain maps, which the
NPCA suspended implementation of at its Jan. 18 meeting. Johnson, who
spoke before West Lincoln council at its Feb. 26 meeting, said he has
two main issues with the proposal. The first is that the report is
based on a number of questionable assumptions. His second concern is
the “autocratic” approach the NPCA took with the project.
“This proposal, in
my view, is very alarming,” said Johnson. “And the process
followed by the NPCA is disturbing.”
The new levels were
approved in March 2011 and the NPCA allowed a one-year transitional
period during which households in the expanded boundary would be able
to build. Residents, including Johnson, fear the changes will impact
their property values and insurance rates and will make it more
difficult to get building permits.
The water level at
Becket’s Bridge, which spans the Welland River on Regional Road 24,
is about 172 metres above sea level, Johnson said. During normal
flood times, the water will rise to about 174 metres. Following
Hurricane Hazel, which could be considered the storm of the century
Johnson said, the river reached a high of 174.65 metres.
At present, the
100-year flood mark, a line which represents the maximum extent of
flooding anticipated as a result of the storm of the century —
which has a one-per-cent chance of occurring each year — is 175.03
metres. The 100-year line also represents the point at which
development is not allowed. The new level jumps up a full metre from
the current level and up to 1.39 metres in parts of Wellandport. In
Wainfleet, 268 households, of about 2,800 in the township, will be
affected by the raised levels, Johnson told members of council. Johnson suspects more homes in West Lincoln will be affected
as the township houses a larger portion of the drainage system.
“In over 57 years,
we haven’t exceeded the Hurricane Hazel flood levels, let alone the
100-year flood lines,” Johnson said. “Remember, the 100-year line
does not guarantee freedom from flooding. It is a line representing a
one-per-cent chance of flooding in any given year. Given the
restrictions on residents along the river and the potential
implications for the community as a whole, this proposal needs public
input and review.”
Ald. John Glazier
asked how many hectares the new levels take out of production.
Johnson said the changes do not take land out of production per say,
but restrict what landowners are able to do with their properties.
Ald. Joanne Chechalk
questioned what role the township can play in the process, suggesting
that staff get in contact with the NPCA and come back with a report.
“I would really
like to hear more about this,” she said. “And how we got here.”
While Ald. Sue-Ellen
Merritt cannot argue with the NPCA’s defence that “determining
flood lines is an engineering exercise” and that “holding public
meetings would not change the scientific outcome of the modelling,”
she did question why affected land owners were not notified and what
the consultants used as a basis for the report. Mayor Douglas Joyner,
who sits on the NPCA board, said the answer to Merritt’s first
question was simple.
“The NPCA does not
have to inform people who live around the Welland River and
tributaries,” he said, explaining that it is the NPCA’s mandate
to protect the public from flooding.
Merritt, who said
she was “disappointed in the NPCA and the way it operates, added
the NPCA needs to change its policies to communicate more with
affected residents.
On Jan. 18, the NPCA
voted to downgrade the new levels to tentative status after meeting
with residents to discuss their concerns. “Staff have met with the
prime engineering consultant and asked that they conduct alternate
simplified analyses on certain areas of the system,” said Tony
D’Amario, CAO. “This additional work should validate the existing
and complex dynamic model that has been developed. We believe that
given the extent of the variances from the old to new levels, and the
concerns expressed by residents, that this additional check is
warranted before moving forward with implementation.”
In the interim,
individuals wishing to construct in the now tentative floodplain
expansion area are being advised of the pending levels and that they
should consider undertaking floodproofing measures in accordance with
the appended draft policy.
The NPCA has also
established a working committee comprised of board members and staff
to develop a process for implementing new regulatory levels for the
entire Welland River. The NPCA does not expect any new information
until the end of June.
Labels:
climate change,
conservation authority,
drainage,
flooding,
floods,
NPCA,
west lincoln
Friday, October 7, 2016
State of emergency declared in Windsor amid severe flooding
The worst-hit parts of Windsor received 156 mm of rain. Windsor's 311 service centre line had received 2,400 calls by Friday night, 1,500 of which related to basement flooding.
The Mayor of Windsor says the flood exceeds the one in one hundred years storm. He also says that these events are no longer random events.
View the video on the site below as it relates to the content on this site:
Source: https://www.theweathernetwork.com/news/articles/state-of-emergency-declared-in-windsor-100--mm-of-rain/72780
The Mayor of Windsor says the flood exceeds the one in one hundred years storm. He also says that these events are no longer random events.
View the video on the site below as it relates to the content on this site:
Source: https://www.theweathernetwork.com/news/articles/state-of-emergency-declared-in-windsor-100--mm-of-rain/72780
Tuesday, August 16, 2016
Open letter to Public works Director of West Lincoln
Open
Letter To Public Works & Engineering Department
XXXXX
XXXXXX – Director of Public Works & Engineering
West
Lincoln Township
318
Canborough St. P.O Box 400
Smithville,
ON LOR 2AO
Re:
Van Buuren Municipal Drain Flooding
Dear
Mr. Xxxxx Included here in you will find my response to your letter
dated August 3rd , 2016 were in you deny drainage issues and direct
me to hand picked quotations from the Drainage act.
As
the earth's climate changes, fatal floods seem to have become an
increasingly prevalent threat. Municipalities should make sure that
decisions and appropriate improvements are just in light of projected
climate impacts.
I
submit that the Van Buuren Municipal Drain extension “A” was a
mistake, not just because the last Drainage Superintendent told us
this, but it was a engineering mistake.
By
the way engineering is spelled that way, not as how you spell it
“engineeering” ,
(see
letter from xxxxx, Director of Public Works ).
The
header of your letter should at lease look like you know what hell
your doing. Your welcome. Oh, by the way we don’t live on xxxxx
“Side Road” either.
A
report from the United Nations Office for Disaster Risk Reduction
notes that in 2015, three of the world's top 10 natural disasters by
number of fatalities were floods.
In
the U.S., floods are listed as the number one natural disaster, with
total flood insurance claims averaging over $3.5 billion U.S. dollars
per year from 2005 to 2014, the U.S. National Flood Insurance Program
reports.
The
Intergovernmental Panel on Climate Change (“IPCC”) Fifth
Assessment Report indicated that precipitation events are very likely
to become more intense and more frequent in Canada.
Its
getting closer. its time to get prepared.
Conservation
authorities may thus be expected by courts to take action in
enforcing their object of preventing flooding. Authorities are
responsible for being knowledgeable about flood prone zones ongoing
monitoring and maintenance obligations. Municipal standards and other
criteria for design and maintenance are usually based on a sub
watershed or flood study, and often built to accommodate the “100”
-year storm” or regional requirements.
We
will be doomed when the Van Buuren “Drain gets a “100”-year
storm.
Unfortunately it is foreseeability going to inevitably happen, it is unavoidable. Unfortunately the Van Buuren Municipal Drain is not engineered for the “100” -year storm. It has trouble handling normal events as you can clearly see the drain running at full capacity during normal events in this video; http://s593.photobucket.com/user/Bears_world/media/Public/Grimsby%20Flooding%20West%20Lincoln/Video.mp4.html
According to the township director of
Public works & “ENGINEEERING DEPARTMENT”, there was a full
clean out of the Van Buuren Municipal drain in 2015.
Good, ok so isn’t that was is
suppose to happen? Lets have a parade and get on with it, It has
helped a great deal but the township has come up short when it thinks
that they are finished, and that is all that had to be done to relive
the flooding. They created there madness, by over development of this
area without the infrastructure to support it. There has been too
much Development and land filling in this area changing the grades
and the natural flow of water courses everywhere we look.
Did you know that Provincial
governments can be named as defendants in civil proceedings related
to flooding. It is not unusual for a provincial government to be sued
for negligence? Were not talking about only the Drainage act now,
still willing to go down with the ship?
Relevant Information
Drainage Act, R.S.O. 1990, c. D.17
15. Subject to section 32, every drainage works constructed under this Act shall be continued to a sufficient outlet. R.S.O. 1990, c.D.17, s.15.
We
do not have a sufficient outlet.
32. Where, in the opinion of the engineer, the cost of continuing a drainage works to a sufficient outlet or the cost of constructing or improving a drainage works with sufficient capacity to carry off the water will exceed the amount of injury likely to be caused to low-lying lands along the course of or below the termination of the drainage works, instead of continuing the works to such an outlet, or making it of such capacity, the engineer may include in the estimate of cost a sufficient sum to compensate the owners of such low-lying lands for any injuries they may sustain from the drainage works, and in the report the engineer shall determine the amount to be paid to the owners of such low-lying lands in respect of such injuries. R.S.O. 1990, c.D.17, s.32.
We
request compensation.
Improving, upon examination and report of engineer
78. (1) If a drainage works has been constructed under a by-law passed under this Act or any predecessor of this Act, and the council of the municipality that is responsible for maintaining and repairing the drainage works considers it appropriate to undertake one or more of the projects listed in subsection (1.1) for the better use, maintenance or repair of the drainage works or of lands or roads, the municipality may undertake and complete the project in accordance with the report of an engineer appointed by it and without the petition required by section 4. 2010, c.16, Sched.1, s.2 (27).
Projects
(1.1)
The projects referred to in subsection (1) are:
1.
Changing the course of the drainage works.
2.
Making a new outlet for the whole or any part of the drainage works.
3.
Constructing a tile drain under the bed of the whole or any part of
the drainage works.
4.
Constructing, reconstructing or extending embankments, walls, dykes,
dams, reservoirs, bridges, pumping stations or other protective works
in connection with the drainage works.
5.
Otherwise improving, extending to an outlet or altering the drainage
works.
6.
Covering all or part of the drainage works.
7.
Consolidating two or more drainage works. 2010, c.16, Sched.1, s.2
(27).
Your
letter explains that “There have been no other recent complaints
of flooding in the area”
You
do know we are in a drought right?
Your
letter letter says “There has been no significant flooding
occurrences in the last 2 years in the area” , does that
mean that the insignificant flooding just didn’t take any lives?
What is your point. According to xxxxxxx -my neighbour, there was a
complaint you have about his yard flooding caused by the Van Buuren
Drain extention “A”.
There
are pictures.
You
state in your letter “All roadside ditching on xxxxxx
was cleaned and upgraded in 2016 to allow free flow of water to the
inlet of the Van Buuren drain extension.”
Completely
false! I don’t know where your getting your information but my
neighbours roadside ditch is still not working, and the 3 culverts on
our side have not been “cleaned and upgraded”. We
still would like the roadside ditch cleaned to the corner, the way it
was back in 2000!
Your
letter says “The Van Buuren main drain underwent a full cleanout
in 2015. There are no known issues or complaints that occurred during
the maintenance work.”
Yes
and the work did not need the police out here to get it done -like
the last time at my neighbours, when the township made the extension
“A” go threw their yard forcefully like were living in Russia.
The under sized, underground portion comes out at a “T” into our
problematic ditch outlet. There were “no issues” this time
because it was a good decision, so whats your point?
By
the way all that water coming from the Micheal street development
into a “T” added to our problematic, unmaintained, ditch outlet
-blocks our outlet in our natural water course, that you hooked up a
municipal drain into.
Again,
please remove the debris from the Van Buuren drain extension “A”,
there are giant hills of grass being piled up all along side the
municipal drains banks, when the drain backs up it will flood us all
out again.
Again,
you are hereby also notified that the stagnant water issue is back.
Please
seriously reconsider your position regarding your responsibilities as
you will be held accountable.
Looking
forward to hearing from you as soon as possible in this regard, thank
you.
Sincerely,
Mr.
xxx
xxxxxxxx
Admin,
Van
Buuren Drain Flood Relief Alliance
Grimsby
Floods Westlincoln
Cc:
Acting Drainage Superintendent West Lincoln -xxxxxxx
Cc:
Ministry
of Natural Resources and Forestry xxxxxxxx
NO
NAMES HAVE BEEN POSTED ON THIS PAGE AT THIS TIME
Labels:
advocacy,
advocate,
climate change,
conservation authority,
director of public works,
drainage,
flood relief,
flooding,
floods,
van buuren drain,
west lincoln
Subscribe to: